ACWA Power Company announces that it has received a notification from the Project Company stating that it has achieved the Commercial Operation Date for the Riverside BESS Project

Element ListExplanation
Announcement Detail acwa announces that it has received, on 11 February 2026, a notice from its Project Company engaged in developing a 334 MW/501 MWh Battery Energy Storage System (BESS) of the Riverside Solar project (Plant 2), notifying the commencement of full commercial operations, following a confirmation issued by its Client JSC “National Electric Grid of Uzbekistan” that the Commercial Operation Date in respect of Plant 2 has been achieved.

acwa owns 100% stake in the Project Company which operates the 200 MW Riverside Solar photovoltaic power plant (Plant 1) and 334 MW/501 MWh Battery Energy Storage System (Plant 2) located in Tashkent region of the Republic of Uzbekistan